In Karaganda region launched the third solar power station

In the village of Agadyr, Shet district, with the participation of the deputy akim of the region Almas Aidarov, the grand opening of a solar power station with a capacity of 50 MW on an area of 125 hectares took place. The project cost amounted to 55 million euros.

The project initiator and equipment supplier was a German company with many years of experience in the development of projects and the introduction of renewable energy technologies.

The main structural element of the Akadyr SES is the park of solar photovoltaic power plants. In order to achieve optimal results, the park is divided into 35 structurally identical sections.

In Karaganda region, purposeful work is being carried out to fulfill the order of Elbasy - on the need to develop a "green" energy.

Recall, to date, two solar power plants are already operating in the region. One in Saran with a capacity of 100 MW, the other in the village of Gulshat at 40 MW. Thus, three green sources are capable of generating almost 200 MW of energy.